NSW Agencies Lost $246M on Failed IT Projects

The state's Auditor-General has found NSW agencies spent about $246 million over three years on IT projects that were later cancelled or abandoned. The figure comes from State agencies 2026, tabled in NSW Parliament on 26 November. It reviewed IT projects at 14 agencies that together spent more than $3 billion on IT capital between 2023-24 and 2025-26.

The $246 million comprises $99.8 million in write-offs and $146 million spent on an abandoned cloud-based application.

That application came from stage 2 of Transport for NSW's Intelligent Congestion Management Program. Approved in 2017, the program closed about 30 months late at a cost of around $146 million. Transport for NSW could not use the delivered platform, which its review found was not fit for purpose.

Post-implementation reviews pointed to frequent changes in leadership and personnel, limited business sponsor involvement, ineffective vendor management and no effective assurance plan. Internal review had indicated that only 8.8% of expected benefits were achievable.

The contract model also gave the supplier significant discretion to define the solution requirements, with ownership of the intellectual property resting with the vendor.

Most projects ran late. Eleven of the 14 projects assessed ran past their planned timeframes, eight by more than a year and one by more than five years. Six exceeded, or are expected to exceed, their original budgets by a combined $179 million.

Agencies blamed solution design and integration challenges, changing business requirements, machinery-of-government changes, scope changes and vendor performance. Several also cited weaknesses in their own governance and assurance.

Business Cases Rarely Held

Every project had an approved business case before it started. Yet 12 of the 14 later needed revisions, significant scope changes or a new delivery model. Budgets for three did not fully account for whole-of-life capital and recurrent costs.

The TAFE NSW Student Management System shows how far costs can move. Its original business case set a capital budget of $85 million. After significant issues with the vendor-developed solution, TAFE NSW brought development in-house and the estimated capital cost rose to $181 million.

Phase 1 went live in October 2025. Defects in its year-end revenue recognition functions required an interim workaround, and TAFE NSW plans to realign the program's benefits during 2026-27.

Transport for NSW also spent $28.1 million testing the State Digital Assets platform for RegStar. That program is meant to replace the legacy DRIVES licensing system. The State Digital Assets Reuse Policy required it to explore that platform first. After more than a year, it found the platform unsuitable and ended the proof of concept in August 2025.

Write-offs were concentrated in three agencies. Transport for NSW accounted for $73.3 million, Insurance and Care NSW for $20.9 million and NSW Police Force for $5.6 million.

Of the four agencies that cancelled projects, three did not complete a post-implementation or post-cancellation review. One business case lacked a cost-benefit analysis, and one agency did not report its cancelled projects to stakeholders.

Weak controls led agencies to incorrectly capitalise $318 million in IT project costs over the three years, including the abandoned application. The Auditor-General said this reduced transparency and accountability over project costs and outcomes.

Public reporting was absent across the board. For all 14 projects, agencies did not publish costs, original budgets, budget variations, delivery timelines or scope changes. Of five completed projects, two did not deliver all the core systems in their business case, and two were never formally evaluated.

Access Controls Fall Short

The financial audits also found IT control weaknesses. Privileged user activity went unmonitored, access reviews were incomplete or late, and some former staff kept application access after their last working day.

One of the year's six high-risk findings involved Transport for NSW, where 290 users could view and modify sensitive employee information. Of those, 247 could access other employees' bank details.

At Insurance and Care NSW, 37 users held elevated access to the live SAP system, and three could delete system change history records. A privileged service account used by an SAP support consultant could manage users and security settings, but security audit logging was not enabled.

Some payroll payment files were not encrypted. The Lord Howe Island Board has yet to resolve recommendations, first raised in 2018, to strengthen its IT governance and control environment.

System migration carried its own risks. After the move to the MyWorkZone platform, Government Shared Services paid 37 invoices totalling $5.5 million a second time. The money was recovered, and a future Audit Office performance audit will examine MyWorkZone.

On transparency, the Auditor-General pointed to its Capital projects 2025 report. That report recommended the NSW Government disclose expected total costs, completion dates and scope changes by 30 June 2027. Agencies should apply the same standard to major IT projects, the Auditor-General said.

 