Seven UK police forces have signed contracts with Mark43 for a new cloud-native records management system, four years after NSW Police terminated its core systems contract with the US vendor.
The Police and Crime Commissioners for Bedfordshire, Cambridgeshire, Essex, Hertfordshire, Kent, Norfolk and Suffolk confirmed the deal on 19 November. Contract signing moves the consortium’s RMS Gen 2 programme into implementation.
Mark43 RMS will replace the forces’ existing Athena system across intelligence, investigation, case management and custody. It is expected to serve about 30,600 users. Accenture is supporting the rollout.
Jane Gyford, Senior Responsible Officer for the programme, described the signing as “a landmark moment” for the consortium.
Mark43 CEO Bob Hughes said the agreement reflected “growing demand for modern, cloud-native technology”. The company already works with Cumbria Constabulary, Greater Manchester Police and the SBA Police Cyprus.
Mark43’s Australian history is more troubled. In March 2020 NSW Police selected Mark43 and Unisys to build its Integrated Policing Operating System (IPOS). IPOS was to replace the Computerised Operational Policing System (COPS), in service since 1994.
NSW Police terminated the contract in June 2022. Mark43 sued in the NSW Supreme Court, and the force said it would cross-claim to recover its losses.
Then Commissioner Karen Webb told a Legislative Council budget estimates hearing in November 2023 that the matter had been settled “with terms of confidentiality”.
At the same hearing, Deputy Commissioner Kenna Ackley said the force had made “considerable progress” since the pivot from Mark43. She said some capability would arrive sooner than the force had envisaged under the original contract.
Greens MLC Abigail Boyd told the hearing that NSW was the only state unable to record why sexual assault victims withdraw their cases, because of its outdated system.
A May 2026 NSW Auditor-General report, Upgrades to core policing technology, examined what went wrong. It does not name the supplier, but describes the 2020 prime contractor as an overseas start-up.
The audit found external advisers had warned about the firm’s financial position, its limited experience at comparable scale and “delivery optimism”. The supplier could not deliver a forensics and exhibits system, and its minimum viable CAD capability was delayed by several years.
The force terminated under early termination clauses after the supplier missed contractual milestones. Close to $A20 million was lost, including about $15 million paid to the supplier. The August 2023 settlement amount was not disclosed.
NSW has since abandoned the single-vendor model. Its 2024-25 tenders for a new CAD system and the COPS replacement set minimum staff and revenue thresholds, effectively excluding start-ups.
The setback has been costly. The audit found completion has moved from June 2027 to June 2031, and the force needs about $A493 million in additional funding.
By December 2025 it had spent $155 million, or 47% of its $328 million capital allocation. Only one of five core systems, the NEXUS forensics and exhibits system, had been fully replaced.
Officers still re-enter the same information several times. In one $4 million fraud investigation, about 700 exhibits were entered manually into four separate systems.
A new CAD system is due to go live in November 2027. Four vendors were shortlisted for the first phase of the COPS replacement, with a prototype due by the end of 2026.